Paving Construction Update

Paving Construction Update for the following areas: Croft Regis Road, Cobleigh Street, Hooper Street, Parker Street, Dean Street, Webster Street, Forest Road, Redwood Road and Fairview Street, Wildwood and Mayfair.

NO ON STREET PARKING ON ANY OF THESE ROADS DURING CONSTRUCTION HOURS

REMOVE ALL BASKETBALL HOOPS, ROCKS AND ANY OTHER OBSTRUCTIONS FROM THE ROADWAY AND MOVE THEM AT LEAST 10 FEET AWAY FROM THE ROAD

Milling on the roads in the Croft Regis/Fairview neighborhoods will begin on Tuesday, August 6th. The contractor will begin on Croft Regis and make the way down to Fairview. Once Fairview is complete, the trucks will mobilize to milling on Wildwood and Mayfair. Casting crews will work on adjusting castings to the roads that were milled the previous day. Daily weekday work to start at 7am and end at 5pm. 

Paving will begin on Wednesday, August 14th and anticipated to end around Monday, August 19th. The schedule is subject to change based on weather or other unforeseen factors.